Building Division
Building Permit Turnaround Time
| Table 1.3.1.3 | ||
| Period Within Which Permit Shall be Issued or Refused | ||
| Forming Part of Article 1.3.1.3. | ||
| Row Number | Class of Building | Time Period |
| 1 |
|
10 days |
| 2 |
|
15 days |
| 3 |
|
20 days |
| 4 |
|
30 days |
Note: The above time frames apply when the applications meet Division C Article 1.3.1.3 of the Ontario Building Code which includes the following conditions.
- payment is made of all fees that are required
- the application is accompanied by the plans and specifications prescribed by the applicable by-law, resolution or regulation
- the proposed construction or demolition will not contravene any applicable law
- the applications are complete
Town of Georgina