Overview
The Town is working to make Lake Drive safer for all, promote active transportation and maintain good traffic flow. A planning study, including extensive public consultation, was completed in 2023 and resulted in direction from Council to begin the first phase of improvements to Lake Drive.
Phase 1 of the Lake Drive Improvements project focuses on implementing seasonal one-way vehicle traffic and a multi-use path along Lake Drive between Metro Road/Varney Road and Dalton Road. This will incorporate transition zones at the east and west ends of the one-way lane and include directional signage, pavement markings and lane separators. Vehicle traffic in the one-way zone will be west-to-east along the southern portion of the road. The bi-directional multi-use path will be in the north lane, separated from vehicle traffic. The multi-use pathway and one-way vehicle lane will be in place during the high-traffic summer months and Lake Drive will be returned to a two-lane, two-way road for the remainder of the year.
Background
- The Lake Drive Functional Assessment study was completed in 2023. This planning study included extensive public consultation, provided high-level analysis of design alternatives and made recommendations for the implementation. The planning study was the precursor to the current Lake Drive Improvements – Phase 1 project.
- The objectives of the Phase 1 project include:
- Seasonal (i.e. summer months) implementation of:
- A multi-use pathway connecting North Gwillimbury Park to Dalton Road
- Separated single lane, one-way vehicular traffic moving from west to east in the section from Metro Road/Varney Road to Dalton Road
- Measures required to maintain timely access for emergency response vehicles
- Transition zones at each end of the Phase 1 segment
- Lane separators, signage and pavement markings to ensure clear directions for use of the road
- Continued smooth traffic movement and access for operation and service vehicles
- Traffic calming features as may be warranted
- Conversion to two-lane, two-way vehicular traffic for the remainder of the year
- Seasonal (i.e. summer months) implementation of:
- In early summer 2024, Chisholm Fleming and Associates was awarded the engineering assignment for the project.
- The main tasks included in the design phase of the engineering assignment include field investigations, preliminary design, stakeholder communications, detailed design and tendering.
- As part of the preliminary design task, a communications plan will be developed and implemented to guide communications with key stakeholders.
Project update
November 2024
The engineering design stage of phase 1 of the Lake Drive Improvements began in summer 2024.
The following briefly describes key aspects of the project:
Current status
- The project kick-off meeting occurred in June 2024
- Work has been completed on:
- Background information collection and review
- Site investigations
- Communications Plan
- Draft Preliminary Design
- November 20, 2024 Council report providing an update on status
- The following tasks are nearing completion:
- Final Preliminary Design
- Targeted stakeholder group discussions
Next steps
- Roll out of the communications plan including:
- Letters to residents, on-street signage, social media posts, etc.
- Complete the detailed design design
Photos and videos
Conceptual rendering of multi-use pathway
Timeline
Timeline
2024
- Project launched
- Engineering preliminary design
- Engineering detailed design
2025
- Tendering and public notification
- Implementation (spring 2025)
Public engagement
The project will include the following public engagement activities:
- Creation and posting of project-related information and regular updates to the Town-hosted project webpage and social media
- Focused discussions with stakeholder groups
- Distribution of letters/notices to local residents and businesses
Town contact
Owen Sanders, Senior Project Manager
osanders@georgina.ca
905-806-7470
Consultant
Paul LaPalme
Project Manager
paul.lapalme@chisholmfleming.com
Important Links
Lake Drive Functional Assessment
The Lake Drive Functional Assessment planning study was completed in 2023 an included extensive public consultation, high-level analysis of alternatives and recommendations for phasing and preferred concepts to be carried forward for design and implementation.
Lake-to-lake Cycling Route and Walking Trail
The Lake Drive Improvements – Phase 1 project encompasses a significant portion of the planned “Lake-to-lake Route,” which is intended to link Lake Ontario to Lake Simcoe.
Documents
Frequently Asked Questions
Why is the Town undertaking the Lake Drive Improvements project?
Lake Drive is a unique and popular feature of the Town of Georgina because of its beautiful, natural setting following the shoreline of Lake Simcoe. Concerns have long been expressed that the narrow and curving roadway of many portions of Lake Drive poses problems for the mix of pedestrians, cyclists and motorists. The Town is taking action to improve the safety and utility of Lake Drive for all users, while amplifying the value of Lake Drive as a local asset.
When will this project be implemented?
Engineering design of Phase 1 is underway and planned to be completed early in 2025. Phase 1 modifications to Lake Drive are targeted to begin in spring 2025.
Will the improvements be permanent?
The planned one-way traffic and multi-use path will be implemented seasonally over the summer months with Lake Drive returned to two-way traffic during the remainder of the year.
Which way will vehicle traffic drive?
Seasonal one-way vehicle traffic will travel west-to-east, from North Gwillimbury Park towards Dalton Road.
How is this project related to the previous Lake Drive Functional Assessment Study?
The Lake Drive Functional Assessment Study occurred in 2023 and was a precursor to the current Lake Drive Improvements – Phase 1 project. The study provided the recommended phasing and preferred design alternatives to be implemented along Lake Drive South, Lake Drive North, Lake Drive East, and Hedge Road. The study also included extensive public consultation including:
- Letters to residents
- Webpage updates
- Two virtual workshops
- Beach pop-up sessions
- Public Information Centre
The key takeaway from these public consultations was that the majority of feedback received was to implement a one-way road along a portion of Lake Drive, with the other lane being a bi-directional multi-use pathway.
How is this project related to the Waterfront Parks Master Plan?
This project is separate from the Waterfront Parks Master Plan, which has a long-term implementation horizon extending past 2030. The project teams coordinate and work together to achieve integration of planned activities between the two projects.